Determine the labor quantity variance


Problem 1: Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows:

Direct material of 6.00 yards at $5.25 per yard

Direct labor of 3.00 hours at $18.00 per hour

Overhead applied per sleeping bag at $18.00

In the month of April, the company actually produced 4,900 sleeping bags using 24,100 yards of material at a cost of $5.70 per yard. The labor used was 11,500 hours at an average rate of $19.50 per hour. The actual overhead spending was $96,200.

Determine the materials price variance and round to the nearest whole dollar. Enter a favorable variance as a negative number. Enter an unfavorable variance as a positive number.

Problem 2: Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows:

Direct material of 5.00 yards at $5.00 per yard

Direct labor of 2.50 hours at $18.00 per hour

Overhead applied per sleeping bag at $18

In the month of April, the company actually produced 5,100 sleeping bags using 26,800 yards of material at a cost of $5.30 per yard. The labor used was 12,250 hours at an average rate of $18.50 per hour. The actual overhead spending was $96,200.

Determine the labor quantity variance and round to the nearest whole dollar. Enter a favorable variance as a negative number. Enter an unfavorable variance as a positive number.

No matter how complex and difficult the assignment is, by availing our Materials Price Variance Assignment Help service, you will definitely score higher academic grades all along with comprehensive knowledge.

Tags: Materials Price Variance Assignment Help, Materials Price Variance Homework Help, Materials Price Variance Coursework, Materials Price Variance Solved Assignments, Favorable and Unfavorable Variance Assignment Help, Favorable and Unfavorable Variance Homework Help, Labor Quantity Variance Assignment Help, Labor Quantity Variance Homework Help

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Determine the labor quantity variance
Reference No:- TGS03031582

Expected delivery within 24 Hours