Determine the impact to the overall profit if the manager


On the SOLVER sensitivity report, the labor shadow price is $30, with an allowable increase of 8 and an allowable decrease of 8. The model attempts to optimize profit. Determine the impact to the overall profit if the manager increases the available labor by 4 hours. Input a negative value to indicate a decrease. Positive numbers to not require a "+" sign entry.