Determine the expected completion time and variance for


Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table:

Activity

Time (Days)

Immediate Predecessors(S)

a

m

b

A

3

6

8

-

B

2

4

4

-

C

1

2

3

-

D

6

7

8

C

E

2

4

6

B, D

F

6

10

14

A, E

G

1

2

4

A, E

H

3

6

9

F

I

10

11

12

G

J

14

16

20

C

K

2

8

10

H, I

a) Determine the expected completion time and variance for each activity.

b) Determine the total project completion time and the critical path for the project.

c) Determine ES, EF, LS, LF, and slack for each activity.

d) What is the probability that Kelle Carpet and Trim will finish the project in 40 days or less?

Solution Preview :

Prepared by a verified Expert
Operation Management: Determine the expected completion time and variance for
Reference No:- TGS02156834

Now Priced at $30 (50% Discount)

Recommended (92%)

Rated (4.4/5)