Determine the critical path and project duration


The following information is known about a project.

Activity Activity Time (days) Immediate Predecessor(s)
A 7 -
B 2 A
C 4 A
D 4 B, C
E 4 D
F 3 E
G 5 E

Draw the network diagram for this project, determine the critical path and project duration and calculate the slack for each activity.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Determine the critical path and project duration
Reference No:- TGS080164

Expected delivery within 24 Hours