Determine the costs involved to crash the project


Assignment:

The laurenster corporation has determined the client will pay them a $10,000 bonus if they complete the project in 14 weeks or less. the associated normal times and costs as well as the crash times and costs are shown below. Considering the costs involved to crash the project determine if the laurenster corporation should crash the project to 14 weeks to receive the bonus.

(Please respond asap as I exams tomorrow. I am unable to understand how to determine which activity to crash. What is the factor to chose the same)

Activity Normal Time Crash Time Normal Cost Crash Cost
A 3 2 600 1200
b 6 4 1200 2400
c 5 2 1200 2400
d 4 3 1200 1800
e 7 6 1200 1800
f 7 4 1200 3000
g 5 1 2400 4800
h 5 2 1200 3000
i 5 3 1800 2400
j 2 2 300 300
k 4 4 300 300
l 3 3 300 300

Solution Preview :

Prepared by a verified Expert
Cost Accounting: Determine the costs involved to crash the project
Reference No:- TGS02090743

Now Priced at $30 (50% Discount)

Recommended (91%)

Rated (4.3/5)