Determine the amount of slack in each of a projects


Determine the amount of slack in each of a project's activities (presented below), and identify the critical path.

Activity Duration
a (1-2) 4
c (2-3) 6
e (4-5) 9
f (5-6) 5
d (2-6) 2
g (6-7) 3

Formula: Slack time = LS-ES or LF-EF.

 