Determine the a balance on the job cost sheets for each job


Problem - At the end of April, Cavy Company had completed Job 766 and 765. Job 766 is for 675 units, and Job 765 is for 900 units. According to the individual job cost sheets the information is as follows:

Job

Direct Materials

Direct Labor

Machine Hours

 

 

 

 

Job 765

$5,670

$3,500

27

Job 766

$8,900

$4,775

44

 

 

 

 

Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $200 per hour, determine the (a) balance on the job cost sheets for each job, and (b) the cost per unit at the end of April.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Determine the a balance on the job cost sheets for each job
Reference No:- TGS02562189

Now Priced at $25 (50% Discount)

Recommended (97%)

Rated (4.9/5)