Determine project-s net present value


The Greasy Spoon Restaurant is thinking of the project with the initial cost of $525,000. Project will not produce any cash flows for first 3 years. Starting in year four, project will produce cash inflows of $721,000 a year for 3 years. This project is risky, so firm has allotted it discount rate of 16%. Determine project's net present value?