Determine project expected completion date


Development of the new deluxe version of the particular software product is being considered. Activities essential for completion of the project are given in the table below along with costs and completion times in weeks:

Activity

Direct Costs

Cost

per crash

($)

Max. Crash Time

(week)

Normal

Crash

Time (week)

Cost

($)

Time (week)

Cost

($)

A

5

500

4

600

100

1

B

10

1200

6

2000

200

4

C

13

3600

11

4800

600

2

D

3

300

1

600

150

2

E

9

1000

8

1400

400

1

F

10

2400

8

5400

1500

2

G

5

700

5

700

0

0

Paths:

i) A -> C -> F -> G
ii) A -> B -> E -> G
iii) A -> B -> D -> E -> G

i) Determine project expected completion date?                          

ii) Determine total cost needed for completing the project on normal time?                              

iii) If you want to decrease time needed to complete the project to only 29 weeks, which activity must be crashed, and how much will the increase total cost? Illustrate Cost Changes and Activities Changed in workings to get answer.