Determine point estimates for the user stories


Question: Your Agile team has decided to use planning poker to determine point estimates for their user stories. What happens when several members estimate a user story at three points or under and several members estimate the same story at ten points? The points assigned to the story are averaged. The high and low are discarded, and the remaining points are averaged. The user story is changed so everyone can agree upon the point value. The story is discussed again to come to a consensus.

 