Determine if overhead is over- or underapplied for each of


Brief Exercise 159 During 2016, Arb Company incurred the following direct labor costs: January $20,000 and February $30,000. Arb uses a predetermined overhead rate of 120% of direct labor cost. Estimated overhead for the 2 months, respectively, totaled $19,500 and $35,700. Actual overhead for the 2 months, respectively, totaled $25,000 and $33,500.

Calculate overhead applied.

Determine if overhead is over- or underapplied for each of the two months and the respective amounts.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Determine if overhead is over- or underapplied for each of
Reference No:- TGS02594736

Now Priced at $10 (50% Discount)