Determine expected project duration


Using the information given in the following table: (A) Identify the critical path. (B) Determine expected project duration

Activity

Precedes

Duration

Start

A,b,c

-

A

D

5

D

F

6

F

G

2

B

E

5

E

F

9

C

H

4

H

G, i

6

G

End

3

I

End

1