Determine earliest start time es earliest finish time ef


Question: A company needs to manage a project which consists of the following set of activities.

Activity

Days

Required

Predecessor

Activities

A

5

-

B

6

--

C

9

B

D

9

A, C

E

3

A

F

20

D, E

Draw an AON network.

- Determine Earliest Start time (ES), Earliest Finish time (EF), Latest Start time (LS), Latest Finish time (LF), and Slack for all the activities.

- What is the critical path for the project and how long should it take to complete it?

- Identify each path through the network using activity name (example: A, B etc.) from beginning to end, and its expected length of time.