determine critical pathdetermine critical path


Determine Critical path

Determine critical path and also need help in finding how to reduce the project time by a number of weeks.

Activity Immediate Predecessor Time (in weeks)
A none 4
B A 2
C A 4
D A 3
E B,C 5
F C 6
G D 2
H E 3
I F,G 5
J H,I 7

1. Draw the network diagram.
2. Find the critical path.

3. If activities A and J can't be shortened, yet activities B through I can be shortened to a minimum of one week at a price of $10,000 per week, which activities whould you shorten to cut the project by four weeks?

Request for Solution File

Ask an Expert for Answer!!
Business Management: determine critical pathdetermine critical path
Reference No:- TGS0483097

Expected delivery within 24 Hours