Determine critical path and duration of project


Problem:

Refer to the information provided by the following table. Draw the network, compute slacks, determine the critical path(s) and the duration of the project.

Activity

 

Time (day)

Start Node

End Node

1

2

3

1

3

6

1

4

2

2

5

7

2

6

0

3

6

2

4

6

4

5

6

9

5

8

4

6

7

8

7

9

3

8

10

1

9

10

5

Equation: Slack = LF (latest finish) – EF (earliest finish)

Solution Preview :

Prepared by a verified Expert
Project Management: Determine critical path and duration of project
Reference No:- TGS01956369

Now Priced at $20 (50% Discount)

Recommended (97%)

Rated (4.9/5)