Determine and identify the critical path


Problem: Using the data in the table, complete the following

• Draw a network diagram
• Perform the forward and backward pass : determine the ES, EF, LS and LF dates
• Determine and identify the critical path
• What is the duration of the project ?  Which activities have a float ?
• Develop a profile of the amounts to be spent per month based on your project schedule
• What is the total project budget at completion

Activity

Predecessor

Duration

Total Cost

A

-

5

$5,000

B

-

10

10,000

C

A, B

7

7,000

D

C

12

12,000

E

D

15

15,000

F

D, E

12

12,000

G

C, F

8

8,000

I

E, G

9

9,000

J

I

10

10,000

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Determine and identify the critical path
Reference No:- TGS01909482

Now Priced at $25 (50% Discount)

Recommended (90%)

Rated (4.3/5)