Describe what the results of each calculation mean to you


a. Schedule variance (SV)

b. Cost variance (CV)

c. Schedule performance index (SPI)

d. Cost performance index (CPI)

e. Estimate to complete (ETC-first method)

f. Estimate to complete (ETC-second method)

g. Estimate at completion (EAC)

h. To-complete performance index (TCPI)

1. Use the following information to answer parts a through h. Describe what the results of each calculation mean to you as a project manager.

PV = $160,000

AC = $170,000

BAC = $800,000

Percent Complete = 20%