Demonstrate the best possible steps for a project manager


"Organizational Input Requirements" Please respond to the following:

  • Demonstrate the best possible steps for a project manager to take in order to price out a job in which the specifications are not prepared until the job is half over. Provide a rationale for your response.

  • *From the e-Activities, prepare a real-world example of the following task dependency examples:

    • Finish to Start: You must buy a building before you can start to make changes to it.

    • Start to Start: You can start planning the brick design for a patio at the same time that you start to lay its foundation

    • Finish to Finish: If you were buying a house, you would want to be sure that you close the sale of your old house the same time that you close the sale of the house you were buying.

    • Start to Finish: You would want to have set the date and location for your wedding before you send out wedding invitations.