Demand for a certain subassembly in a toy manufacturing


Demand for a certain subassembly in a toy manufacturing facility at the North Pole is 96 items per eight-hour shift of elves. The following six tasks are required to produce one subassembly.

Task

Time Required (minutes)

Predecessor Tasks

a

4

-

b

5

a

c

3

A

d

2

b

e

1

b,c

f

5

d,e

What is the required cycle time? Theoretically, how many stations will be required? Balance the line. What is the line"s efficiency?

 

 

Solution Preview :

Prepared by a verified Expert
Project Management: Demand for a certain subassembly in a toy manufacturing
Reference No:- TGS0921725

Now Priced at $20 (50% Discount)

Recommended (93%)