Defining one flow unit as one minute of work what is the


Pandao Inc. is a fast food restaurant which offers 4 main types of sandwiches: Pando - classic (C), Pando - premium (P), Pando - exotic (E), and Pando - ultimate (U). Every day, the restaurant operates for 10 hours and it is expecting to sell 500 sandwiches. And from the past data, 30% of the demand is for C, 20% is for P, 40% is for E, and 10% is for U.  There are up to five steps in the process of making sandwiches, listed below with activity times. 80% of customers want their sandwich toasted, no matter which sandwich is ordered.

Step

Classic

Premium

Exotic

Ultimate

Prepare bread

.75 minutes

.75 minutes

1.5 minutes

1.5 minutes

Prepare meat

.5 minutes

.8 minutes

1.5 minutes

1.5 minutes

Toast

.5 minutes

.5 minutes

.75 minutes

1 minute

Wrap

.5 minutes

.5 minutes

1 minute

.5 minutes

Checkout

.5 minutes

.5 minutes

.5 minutes

.5 minutes

Suppose that there is one worker at each step. Answer the following questions.

1. Defining one flow unit as one minute of work, what is the capacity per day for the worker at "Toast" step? Round your answer to the nearest integer. Your answer is. 

2. Defining one flow unit as one minute of work, what is the demand rate per day for the worker at "Toast" step? Round your answer to the nearest integer. Your answer is. 

3. The implied utilization rate for the worker at "Toast" step is . Ignore the percentage sign and round your answer to the nearest integer. For example, if your answer is 43.21%, input 43.

Solution Preview :

Prepared by a verified Expert
Business Management: Defining one flow unit as one minute of work what is the
Reference No:- TGS01577810

Now Priced at $15 (50% Discount)

Recommended (98%)

Rated (4.3/5)