Define the systems integration team for project plans


Assignment:

System Integration Project

Application of PERT/CPM

Two international banks are integrating two financial processing software systems as a result of their merger. Preliminary analysis and interviews with all parties involved resulted in the following project information. The "systems integration team" for this project plans to define and manage this project on two levels. The following activities represent an aggregate view, and within each activity is a more detailed view with subtasks and project networks defined. All times are in weeks.

Activity      Immediate        Time

                  Predecessors

 A                 -                   3                  

 B                 A                   1

 C                 A                   2                  

 D               B, C                 3                  

 E                C                    5

 F                C                    3                  

 G                E                    7                  

 H               E, F                  5                  

 I             D, G, H                8                  

As a member of the systems integration team, you have operations management responsibilities. You have been tasked to develop a detailed project plan, to identify alternative project completion dates, and to recommend an optimal project deadline to top management.

You should start with a Gantt Chart that will keep top management temporarily content, while you prepare your PERT/CPM analysis. You need an Activities Time Requirements Table, a Critical Task and Slack Time Table, and a PERT/CPM Network Diagram that displays the critical path. Of course, you will prepare a report for top management with the Background of this systems project, the project deadline Issue to be resolved, the three project deadline Alternatives, an Analysis of the three Alternatives, and your Recommendation.

Attached to your report should be a Gantt Chart, Activities Time Requirements Table, a Critical Task and Slack Time Table, and a PERT/CPM Network Diagram.

Solution Preview :

Prepared by a verified Expert
Management Information Sys: Define the systems integration team for project plans
Reference No:- TGS03159303

Now Priced at $30 (50% Discount)

Recommended (91%)

Rated (4.3/5)