define the highlights of critical path method a


Define the Highlights of Critical Path Method

  • A network analysis technique used to predict project duration by analyzing which sequence of activities has the least amount of schedule flexibility (float)
  • Early dates are calculated by a forward pass using a specified start date
  • Late dates are calculated by a backwards pass using a specified completion date (usually the early finish date)
  • Uses deterministic dates (for example, the most likely date the activity will occur)
  • Single duration estimate for each activity
  • Start date and calculated Early Finish and Late Finish dates for each activity
  • Primary focus when analyzing the project is on calculating float.