Dave is the project manager on a project to install a new privacy fence around a five-star hotel.

The materials for the fence are estimated to cost $230,000. The labor is estimated at $95,000. Miscellaneous costs are estimated at $15,000. And training is estimated at $3,000. Ongoing maintenance is estimated at $20,000.

What is the BAC?

Solution Preview :