Cycle time for the vats is about 22 hours the manager has


A machine cell uses 160 pounds of a certain material each day. Material is transported in vats that hold 22.5 pounds each.

Cycle time for the vats is about 2.2 hours. The manager has assigned an inefficiency factor of 0.06 to the cell. The plant operates on an 8 hour day.

How many vats will be used?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Cycle time for the vats is about 22 hours the manager has
Reference No:- TGS02593914

Expected delivery within 24 Hours