Customers are placing orders at a rate of 6 items per hour


1. Scenario: Customers are placing orders at a rate of 6 items per hour. The value stream has 3 major process steps: Step A processes at 3 items per hour, B at 4 items per hour, and C at 2 items per hour. In this scenario, the throughput rate of the value stream is: a. 2 items per hour b. 3 items per hour c. 4 items per hour d. 6 items per hour

2. During the Measure phase of a Six Sigma DMAIC project, all of the following are done EXCEPT:

a. Measure the Y (in Y=f(x))

b. Measure the causes or Xs (in Y=f(x))

c. Develop a data collection plan

d. Map processes within the scope of the project