Current carrying cost-order cost


Redan Manufacturing uses 2,400 switch assemblies per week and then reorders another 2,400. The relevant carrying cost per switch assembly is $9.50, and the fixed order cost is $1,200.

What is the current carrying cost?

What is the order cost.

Calculate the economic order quantity.