Critique the program provided - find and discuss any


Assignment Overview - This Assignment relates to the following Project:

19735 Project 1 Medium Rise Apartments

Job Address:

2135 The Boulevard, Strathfield, NSW

Job Title:

Proposed Commercial and Residential Development

Client:

AKM Developments

Architect:

Olympic Designs, 55 Olympic Pde, Homebush, NSW

You should obtain the following documents, from the OLS, for the job:

Plans:                                   Page 1  Site Plan

                                            Page 2  Basement 1

                                            Page 3  Basement 2

                                            Page 4  Basement 1 Setout

                                            Page 5  Basement 2 Setout

                                            Page 6  Floor Plan Level 1

                                            Page 7  Floor Plan Level 2

                                            Page 8  Floor Plan Level 3

                                            Page 9  Floor Plan Level 4

                                            Page 10  Floor Plan Level 5

                                            Page 11  Setout Level 1 and 2

                                            Page 12  Setout Level 3 and 4

                                            Page 13  Setout Level 5

                                            Page 14  South Elevation

                                            Page 15  North Elevation

                                            Page 16  East and West Elevations

Bill of Quantities:                   Preliminary Estimate (6 pages)

Your Task for this assessment -

Assume you are the construction manager for a building company contracted to build the Boulevard Strathfield Apartments project.

You should use the Precedence Diagram for the project that you prepared in CPCCBC5002A.

(If you did not complete CPCCBC5002A you will find the information to prepare the diagram at the end of this assessment as an appendix)

Review the overall target schedule for the project carefully, and answer the following questions:

1. Critique the program provided - find and discuss any inconsistencies that you can find. Would you ask for changes to be made, and why?

2. Overall is the schedule realistic or optimistic?

3. Would you accept the schedule and provide it to your client or architect?

4. Assume that construction activities have fallen behind program. Task compression is required. Select Two tasks and outline:

a. Time cost and compression impacts of working overtime each day.

b. Time cost and compression impacts of working 6 days per week.

c. Outline other ways to compress the project schedule.

Attachment:- Assignment.zip

Request for Solution File

Ask an Expert for Answer!!
Dissertation: Critique the program provided - find and discuss any
Reference No:- TGS01670926

Expected delivery within 24 Hours