Critical ratio


Critical Ratio is: A. Greater than one if the job is behind schedule B. The ratio between processing time and the idle time of the process C. Two of the listed answers D. The ratio between remaining processing time and the remaining time until due date E. The ratio between remaining time until due date and the remaining processing time