Critical path to be taken for reducing the project


Consider the project-related information below.

Activity

Preceding Activities

Time (Weeks)

Crash Time

Crash Cost per week

A

-  

3

2

$7000

B

A

4

2

$5000

C

A, B

2

1

$6000

D

A

3

2

$4000


Which one of the following options is the appropriate course of action to take if you want to reduce the project time by two weeks?

A. Crash A for two weeks because it is the only activity that reduces the time on both critical paths.

B. Crash D for two weeks because you should always crash the least costly alternative first.

C. Crash D for one week and B for one week because you should always crash the least costly alternative on each critical path first.

D. Crash B for two weeks because it is the least costly alternative on the critical path.

Additional Requirement

This question belongs to Operations Management and it discusses about on the appropriate critical path to take which can decrease the project time by two weeks.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Critical path to be taken for reducing the project
Reference No:- TGS01104968

Expected delivery within 24 Hours