Critical path to be taken for project


Consider a project which consists of six activities. The precedence relationships and activity times are as follows:

Activity

Preceding Activities

Time (Days)

1

 

16

2

 

30

3

1

15

4

2

5

5

1

5

6

3, 4

5

What is the critical path for completion of the project?

A. 1 → 3 → 6

B. 2 → 3 → 5

C. 2 → 4 → 6

D. 1 → 2 → 4 → 6