Critical engineering process-engineering bill of material


Discuss the below:

Learning Curves help companies predict the amount of time that it will take to produce "N" number of units of a large capital goods order such as military tanks or military aircraft.

How many hours will it take to build M-1 Tank No.5 given the following data: 85% Learning curve...6,000 hours for the first tank... Hours for M.1 Tank # 5

How many total hours will it take to build all M-1 Tanks from Unit 1 through Unit 15 given the following data: 85% Learning curve ....6,000 hours for the first tank .... Hours for all M-1 Tanks 1 through 15

What critical Engineering process is used to keep the B-52 Bombers in service since 1952:

The Robot Asimo has been developed by what Japanese company?

Name three data elements that are shown on the Engineering Bill of Material: