Creating a flexible budget performance report


Problem: Preparing a Flexible Budget Performance Report

Canyonland Boat Charter Service rents live-aboard houseboats for cruising on the lake that traverses most of the Glen Canyon National Recreation area in Southern Utah. The company bases its overhead cost budgets on the following data:

Variable overhead costs

 

 

 

Cleaning

$

72.50

per charter

Maintenance

$

56.25

per charter

Park usage fees

$

15.75

per charter

 

 

 

 

Fixed overhead costs

 

 

 

Salaries and wages

$

7,860

per month

Depreciation

$

13,400

per month

Utilities

$

720

per month

Moorage

$

3,670

per month


Each time a boat is chartered, whether it is for one day or a week, certain costs must be incurred. Those costs are listed above under the variable overhead costs. For example, each time a boat returns from a charter, it must be thoroughly cleaned, which costs $72.50 on average.

In August, the following actual costs were incurred for 140 charters:

Cleaning

$

10,360

Maintenance

$

7,630

Park usage fees

$

2,210

Salaries and wages

$

7,855

Depreciation

$

14,450

Utilities

$

735

Moorage

$

3,950


Due to an unanticipated surge in demand for charters, the company purchased a new boat in August to add to its charter fleet.

Required:
Construct a Flexible Budget Performance Report for Canyonland Boat Charter Service for August.

Canyonland Boat Charter Service
Flexible Budget Performance Report
For the Month Ended August 31

                                                Cost Formula    Actual Costs     Flexible Budget    Variance
                                                (per charter)     Incurred for         Based on
                                                                       140 Charters      140 Charters


Variable overhead costs:

Cleaning
Maintenance
Park usage fees
Total variable overhead cost


Fixed overhead costs:

Salaries and wages
Depreciation
Utilities
Moorage
Total fixed overhead cost
Total overhead cost

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Creating a flexible budget performance report
Reference No:- TGS01909509

Now Priced at $25 (50% Discount)

Recommended (97%)