Create the network diagram in the application of your


Quantitative Methods in Project Management

Problem 1: Given the information provided below (predecessors, normal time, normal cost, crash time (the minimum duration) and crash cost (the cost if crashed to the minimum duration) for an nine-activity (a to i) project) answer the questions (a) through (e) using this template.

Activity

Predecessor

Normal
Time

Normal
Cost

Crash
Time

Crash Cost

a

 

4

$50

2

$150

b

a

4

$40

2

$200

c

b

7

$70

4

$160

d

c, f

2

$20

1

$50

e

c

3

$30

2

$100

f

b

8

$80

5

$290

g

d, e

5

$50

3

$100

h

f

6

$60

 

$180

i

g, h

3

$50

3

$50

(a). Create the network diagram in the application of your choice and then insert a screen shot of the diagram here. The diagram can be created easily in MS Word using the Insert Shapes function.

Enter your network diagram in this space provided (you should delete this text box and use as much space as necessary to display your network diagram).

Identify the critical path of the network, the time, and cost of the normal level of activity for the project:

- The critical path (or paths) is:
- The project duration:

The project cost is:

(b). Calculate the crash cost-per-day (all activities may be partially crashed). Enter your response to question 1(b) in the table provided below

Activity

Normal
Time

Normal
Cost

Crash Time

Crash Cost

Crash
Cost/Day'

a

 

 

 

 

 

b

 

 

 

 

 

c

 

 

 

 

 

d

 

 

 

 

 

e

 

 

 

 

 

f          
g          
h          

(c). Find the optimal way to crash the project by one day.
- What is the projected project cost?
- What is the projected project duration?
- What is the critical path (or paths)?
- What task or tasks were crashed?
Explain the results of your calculations.

(d). Find the optimal way to crash the project by two days.
- What is the projected project cost?
- What is the projected project duration?
- What is the critical path (or paths)?
- What task or tasks were crashed?
Explain the results of your calculations.

(e). Calculate the shortest completion time for the project.
- What is the projected project cost?
- What is the projected project duration?
- What is the critical path (or paths)?
- What task or tasks were crashed?

Explain the results of your calculations.

Solution Preview :

Prepared by a verified Expert
Project Management: Create the network diagram in the application of your
Reference No:- TGS02351285

Now Priced at $30 (50% Discount)

Recommended (93%)

Rated (4.5/5)