Create in microsoft project a wbs and then an aon add at


Based on the following information, create in Microsoft Project, a WBS and then an AON.  Add at least 4 milestones.  Now add a lag of two days to an activity on a noncritical path.

There are five employees involved in these activities.  Assign the tasks to people and create their pay rate, then add a few material resources, and then check to be sure that no one and no equipment is over assigned.  No human can work more than eight hours in a day, nor 40 hours in a week.

Create a Gantt chart to show that you are on time ten days into the project, and another to show that you are late by 2 days.

Now adjust the work week from five days (All of the figures are based on an 8 hour day, working Monday to Friday) to seven days a week, but no one person can work more than 40 hours in any week.  Print out the new ANO and Gantt chart.

Create a split view.

What is the baseline plan?  What is the cost of the project?

Activity           Preceding activities     Best                 Likely              Worst              TE

 

A                                 -                    12                    15                    25                    16

 

B                                 A                    4                      6                      11                    7

 

C                                 -                    12                    12                    30                    15

 

D                                 B, C                8                      15                    20                    15

 

E                                  A                   7                      12                    15                    12

 

F                                  E                    9                      9                      42                    15

 

G                                 D, E                 13                    17                    19                    17

 

H                                 F                      5                      10                    15                    10

 

I                                   G                     11                    13                    20                    14

 

J                                   G, H                2                      3                      6                      3

 

K                                 J, I                   8                      12                    22                    13

The activities can be anything you want.  If you are lost, try constructing a house.

Solution Preview :

Prepared by a verified Expert
Operation Management: Create in microsoft project a wbs and then an aon add at
Reference No:- TGS02857619

Now Priced at $50 (50% Discount)

Recommended (97%)

Rated (4.9/5)