Create gantt chart using ms project


Discuss the below:

Create a solution for Project Management Achieving Competitive Advantage (4th Edition)

Q: Using the following data, enter the various tasks and create Gantt Chart using MS Project. Assign the individuals responsible for each activity and once you have completed the network, update it with the percentage complete tool. What does the Ms Project output file look like?

Activity Duration Predecessors Resource %Complete
A. Research Product 6 - Tom Allen 100
B. Interview Customers 4 A Liz Watts 75
C. Design Survey 5 A Rich Watkins 50
D. Collect data 4 B, C Gary Sims 0

 