Create an ad hoc schedule for the first time units


Assignment:

Q: Invent a unique 4-job task and write down the (ei,pi) for each of them.

ei = execution time

pi = period

j1 = [4,1]

j2 = [5,2]

j3 = [7,1]

j4 = [10,2]

Choose some unsolved task with 4 jobs, and calculate the following: hyperperiod, calculate all the individual jobutilizations, calculate the total utilization [AND COMMENT] and create an ad hoc schedule for the first 20 time units, calculate ea ch job's response time [for the first 20 time units], and the total response time [[for the first 20 time units].