Create a finished goods production plan mrp and component b


Create a finished goods production plan MRP (and component B procurement plan) given the following:

o Production cycle time = 1 month

o Each finished good item requires 2 Part B's; part B has a 1 month procurement lead time

o Beginning finished product inventory is 1,000

o Forecasted sales are as follows:

Month 1: 1,000
Month 2: 1,100
Month 3: 1,150
Month 4: 1,200
Month 5: 1,200
Month 6: 1,300

o Safety Stock: On the first day of each month, you want to have that month's sales already in inventory

o Capacity of the plant is 1,300 units

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Create a finished goods production plan mrp and component b
Reference No:- TGS01073152

Expected delivery within 24 Hours