Costs are 10m 50m 80m and 50m for years 1 to 4 costs are


Construction costs for a petroleum refinery will be spread over a 4-year period. Costs are $10M, $50M, $80M, and $50M for years 1 to 4. Costs are continuous within each year, and i is 15%. What is the PW?