Cost of equity for the project


Problem:

As the CFO of Finance Rocks (FR) Inc., you are considering building a book factory. You determine that you will use a D/E ratio of 2 and that after-tax cost of debt is 5%. To get the cost of equity for the factory you plan to use information from a comparable firm, Accounting Not So Much (ANSM) Inc. The beta on ANSM's stock is 1.2 and its D/E is 1. If the T-bond rate is 6% and the market risk premium is 5.5%. The tax rate for FR and ANSM is 40%.

Required:

Question 1: What is the cost of equity for the project?

Question 2: What is the project's WACC?

Note: Be sure to show how you arrived at your answer.