Control factor unit used in the work measurement study was hundreds of pounds of equipment unloaded or loaded at the dock.

Month         Units of Activities    Material handling cost $
January             1400                         11350
February            1200                         11350
March                1100                         11050
April                  2600                         12120
May                  1800                          11400
June                 2000                          12000
July                  2400                          12550
August              2200                          11100
Sept.                1000                          10200
October            1300                          11250
Novem.            1600                          11300
Decem.            1800                          11700

1) Draw a scatter diagram of the cost data for material handling department.

2) Estimate material handling cost behavior using high low method.

3) Predict company's material handling costs for a month when 2300 units of activity are recorded.

Solution Preview :

Prepared by a verified Expert
Other Management: Cost data for material handling department
Reference No:- TGS01445188

Now Priced at $20 (50% Discount)

Recommended (96%)

Rated (4.8/5)