Correctly layout the project network and identify the


Using Critical Chain Project Management (CCPM) and the same small, typical project network shown above (in Question 1), answer and fully explain your answers each of the questions below. You have only one of the yellow, red, green and blue resources.

Correctly layout the project network (and identify the activities on it) that are the proper Critical Chain. [Hint: to find it, you may have to attempt more than one Gantt Chart (all must be drawn TO SCALE and WITHOUT inserting the buffers).] Explain your answer.

How many resource buffers are needed and where should they be positioned (be sure to explain your answer)?

Where should each Feeding Buffer be located (you can state BETWEEN which two activities any/all of the FB(s) should be positioned or insert properly-sized blocks to denote each into an updated copy of the Gantt Chart you created to answer 2b) and how large should each one be? Be sure your explanation or diagram explains your answer.

How big should the Project Buffer be? How did you determine this?

What is the total project lead time?

 

1129_Untitled.png

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Correctly layout the project network and identify the
Reference No:- TGS02462265

Expected delivery within 24 Hours