Control chart to manage the irregularities


Problem 1: A shirt manufacturer buys cloth by the 100 yard roll from a supplier. For setting up a control chart to manage the irregularities (e.g., loose threads and tears) the following data was collected from a sample provided by the supplier.

SAMPLE                 1  2  3  4  5  6  7  8  9 10
IRREGULARITIES    3  5  2  6  5  4  6  3  4 5

Problem 2: Determine the , Sp, UCL and LCL for a c-chart with z = 2. (Round your answers to 2 decimal places.)

Sp  = ___

UCL = ___

LCL = ___

Problem 3: Suppose the next five rolls from the supplier had three, two, five, three and seven irregularities. What is the UCL? (Round your answer to 2 decimal places.)

UCL = ___

Solution Preview :

Prepared by a verified Expert
Operation Research: Control chart to manage the irregularities
Reference No:- TGS01752585

Now Priced at $20 (50% Discount)

Recommended (93%)