Constructing the network sit preparation


Constructing the network sit preparation project

         TABLE 1 SITE Preparation project

Task              Title                                  Predecessors                             Duration

A           contract approval                      ------                                                5

B             site survey                                 a                                                       5

C          permit application                          a                                                      4

D       grading                                       b, c                                                      5

E      sewer lines                                 b                                                         7

F        base paving                                d                                                          3

G       city approval                             c, f                                                         6  

H        final Paving                           e, g                                                            8    

Using the above information complete the following tasks:

1. Construct this network using Microsoft project 2013

2. Identify the critical path. how long will the project take?

3. Assign and level resources

4. Suppose rose is responsible for activities b and c . are there any resource conflicts? How do we know.

5. Show the same project using a gantt chart and a network diagram.