Question: Construct a Gantt chart for the project described by the following set of activities, and indicates the project completion time and available slack for each activities. Please see the following table:
| |
Activity Predecessor |
Time (Weeks) |
| |
- |
|
|
3 |
| |
- |
|
|
7 |
| |
1 |
|
|
2 |
| |
2 |
|
|
5 |
| |
2 |
|
|
6 |
| |
4 |
|
|
1 |
| |
5 |
|
|
4 |