Constructing a c-chart for process


Assignment:

The Great North Woods Clothing Company is a mail-order company that processes thousands of mail and telephone orders each week. They have a customer service number to handle customer order problems, inquiries, and complaints. The company wants to monitor the number of customer calls that can be classified as complaints. The total number of complaint calls the customer service department has received for each of the last 30 weekdays are shown as follows:

Day  Calls Day    Calls
1        27       16       19
2        15       17       12
3        38       18       17
4        41       19      18
5        19       20       26
6        23       21       31
7        21       22      14
8        16       23       18
9        33       24       26
10      35       25      27
11      26      26      35
12      42      27      20
13      40      28      12
14      35      29      16
15      25      30      15?

a. Construct a c-chart for this process with 3 control limits and indicate if the process was out of control at any time.
b. What nonrandom (i.e., assignable) causes might result in the process being out of control?

Your answer must be typed, double-spaced, Times New Roman font (size 12), one-inch margins on all sides, APA format and also include references.