Construct linear program that minimizes total number


Problem:

Personnel Scheduling- Palm Beach General Hospital is concerned with the staffing of its emergency department. A recent analysis indicated that a typical day may be divided into six periods. In each period a different demand level, measured by "cases," is experienced.

                                    Average Number

          Time Period              of Cases         

7 A.M - 11 A.M                        80

11 A.M. - 3 P.M.                      60

3 P.M.- 7 P.M.                        120

7 P.M.- 11 P.M                        60

11P.M. - 3 A.M.                      40

3 A.M. - 7 A.M.                       20         

Past experience indicated that one emergency room (ER) nurse, is required to handle 2.5 cases each hour. Thus, for example, between 7 A.M. and 8 A.M. there is a need for 8 nurses to handle the 20 cases (80 cases per 4 hours).

ER nurses work in shifts of 8 hours. The normal shifts are:

          7 A.M. to 3 P.M.

          3 P.M. to 11 P.M.

          11 P.M. to 7 A.M.

However, three nurses said that they are willing to start an eight hour shift at 11 A.M. if necessary and two said they will start at 7 P.M. if asked

Required:

Question 1) Clearly state your decision variables and construct a linear program that minimizes the total number of ER nurses to report to duty to cover load requirements.

Solve the given numerical problem and illustrate step by step calculation.