Activity          Predecessors     Activity Time

A                              -                          3

B                              A                         1

C                              A                         6

D                              B                         7

E                               -                          2

F                               D                         9

G                              C, F                    10

H                               C                          3

I                                 H                         4

J                               E, G. I                   2

K                                H                         1