Construct an activity on node diagram to identify the


PROJECT MANAGEMENT / MANAGEMENT OF ENGINEERING PROJECTS

A Project is comprised of 15 tasks.

Tasks 1, 2, 3 and 4 can start concurrently and their durations are 10, 11, 12 and 13 days respectively. Tasks 5, 6, 7 and 8 have durations of 10, 9, 8 and 7 respectively and task 5 can start 5 days after task 1 has started. Task 2 must be completed before task 6 can be started and task 7 follows on from task 3. Task 8 can be started 2 days after task 4 has been completed. Tasks 9, 10, 11 and 12 have durations of 5, 6, 7 and 8 days respectively. Tasks 13, 14 and 15 have durations of 5, 4 and 3 days respectively. Task 9 starts 3 days after task 5 finishes and task 10 starts once tasks 5 and 6 are complete. Task 11 cannot start before tasks 6 and 7 are completed and task 12 is dependent on the completion of tasks 7 and 8. Task 13 commences after tasks 9 and 10 are finished and task 14 cannot start until tasks 10 and 11 are finished. Task 15 can start 3 days after the start of task 11 but only if task 12 is complete. The project is complete when tasks 12, 13, 14 and 15 are complete.

Construct a work break down table showing the interdependencies of the tasks and show this graphically using a flowchart.

Construct an activity on node diagram to identify the critical path, estimated duration of the project and the float of each activity.

Request for Solution File

Ask an Expert for Answer!!
Project Management: Construct an activity on node diagram to identify the
Reference No:- TGS02391835

Expected delivery within 24 Hours