Construct a product structure identify all levels parents


Refer again to Problems 1 and 2. In addition to 100 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change.

Problems 1
Using the information in Problem 2, construct a gross material requirements plan.

Problem 2

The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.

a) Construct a product structure. Identify all levels, parents, and components.

b) Prepare a time-phased product structure.

Request for Solution File

Ask an Expert for Answer!!
Business Management: Construct a product structure identify all levels parents
Reference No:- TGS01660322

Expected delivery within 24 Hours