Miracle Marketing has received the construct from the large pharmaceutical firm to design the nationwide advertising compaign for their recently approved cancer drug. The drug is simply taken, compared with current intravenous drugs, and can be administered from the home. Miracle Marketing has assigned to task a project manager who, in turns has delegated minor sub projects to subordinate managers.
The project was measured using ADM or PERT analysis. Due to extensive length of the project many activities were combined; The folowing is the result.
| Activity |
Time(month) |
| AB |
3 |
| BC |
6 |
| BD |
2 |
| BF |
5 |
| BE |
4 |
| CD |
9 |
| DG |
20 |
| FG |
6 |
| EH |
11 |
| EI |
19 |
| GJ |
1 |
| HK |
3 |
| IL |
9 |
| LM |
12 |
| KN |
7 |
| JO |
4 |
| MN |
15 |
| NP |
13 |
| OP |
10 |
Find out the critical path and expected completion date.